Erect column, torsion box, and stringers. Three crane days with Unit 53 on site — days 1–2 back to back, day 3 after the SCE crossing clearance.
Nothing on the list — add what the crew needs.
Calls, emails, voicenotes, and notes — one stream.
Courtney YaegerNote
Inspector walkthrough
Met the city inspector on site this morning. Everything looks good for the foundation inspection; anchor-bolt photos already in the job.
Courtney Yaeger → Aaron BloomCall
Walked Aaron through erection progress; day 2 torsion box on schedule.